Case study · Sidelca
Major rehabilitation of a high-power motor (7000 kW) for a critical boiler feedwater pump system - Planta Centro
Client: CADAFE Planta Centro Industry: Power / Thermal Generation Location: Planta Centro (CADAFE Morón) and SIDELCA workshops, Valencia
- Equipment: Boiler Feedwater Pump "A" Motor, Unit 4.
1. Executive Summary
- Key Impact: Assured operational availability of Unit 4 at Planta Centro through the major overhaul of a 7000 kW motor.
- Engineering Applied: The project included advanced diagnostic protocols, mechanical assessment and dielectric recovery to guarantee the pumping of feedwater to the boiler, a process vital to power generation.
2. Technical Challenge (The Problem)
The availability of one of the country's most important thermal power plants depended on the integrity of this medium-voltage asset:
- Asset Specifications: Hitachi motor, 7000 kW, operating at 6.6 kV and 1185 RPM.
- Criticality: As a unit dedicated to the boiler feedwater pump, any deviation in mechanical or electrical parameters directly compromises the steam and power generation of the unit.
- Diagnostic Need: The equipment required an in-depth assessment to detect incipient faults in the core and validate the mechanical tolerances of the bearings and shaft.
3. Comprehensive Solution (Engineering by SIDELCA)
SIDELCA carried out a comprehensive maintenance protocol (Overhaul) under international standards:
- Diagnostics and Specialized Testing:
- Core Loss Test: Validation of the magnetic efficiency of the stator.
- Surge Comparison: Detection of turn-to-turn winding faults.
- Mechanical Assessment: Rotor run-out measurement and verification of tolerances at bearing seats and shaft.
- Dielectric and Thermal Treatment:
- Steam cleaning of the winding with mild solvents and repair of lashings.
- High-Grade Varnishing: Application of solvent-free Dolph Class H varnish with a red anti-flash varnish finish.
- Controlled baking processes for the polymerization of the insulation.
- Improvements and Protection:
- Supply and installation of 1000 W (220 V) space heaters to prevent moisture condensation during shutdown periods.
- Installation of a new set of bearings to guarantee minimum friction and operational stability.
4. Results and Testing (Guaranteed Success)
The project concluded with the certification of the equipment within nominal parameters:
- Acceptance Testing: No-load operating protocol at reduced voltage to validate mechanical and electrical stability.
- Dielectric Certification: Validation of the stator's insulation resistance and polarization index.
- Schedule Efficiency: Technical execution completed within 15 to 20 working days.
5. Project Technical Data
| Attribute | Technical Detail |
| Make / Serial | Hitachi / 316647-1 |
| Power | 7000 kW (approx. 9400 HP) |
| Operating Voltage | 6.6 kV (Medium Voltage) |
| Rated Speed | 1185 RPM |
| Dielectric Insulation | Dolph Class H varnish / Anti-flash |
| Service Warranty | 3 months under verifiable normal operation |